Written By: Dennis Ruhlin | Last Updated: November 18, 2026
Time to Read 16 Minutes
You called the National Response Center, maybe DEP too, and the cleanup crew has the sheen under control. Plenty of facility managers figure the reporting is finished at that point, but the federal oil spill prevention rule adds a second, written report for bigger spills. If your facility is subject to the Spill Prevention, Control, and Countermeasure (SPCC) rule, which generally means it stores more than 1,320 gallons of oil aboveground (counting only containers of 55 gallons or more) or more than 42,000 gallons buried, then a single discharge of more than 1,000 gallons to navigable waters or adjoining shorelines, or more than 42 gallons in each of two discharges within any twelve-month period, means you owe the EPA Regional Administrator a written submission within 60 days. The phone call to the NRC doesn't count as that submission.
That written report is the one that gets missed, because it comes due weeks after the emergency is over and nobody's standing in the parking lot reminding you. Below we explain how the NRC, DEP, and EPA reports differ, which spills trigger the EPA submission, what goes in it, what EPA Region 3 can do with it, and how a reportable spill affects a facility that self-certifies its own SPCC Plan. If you're dealing with a spill right now and want a second set of eyes, you can reach out to RMA at any point.
TL;DR
Calling the National Response Center is only the first report. If your facility is subject to the federal SPCC rule and a spill sends more than 1,000 gallons of oil to navigable waters or adjoining shorelines in one event, or more than 42 gallons in each of two events within 12 months, you also owe a written submission to the EPA Regional Administrator within 60 days, with a copy to the state. EPA can then require changes to your SPCC Plan. A spill doesn't automatically end a facility's right to self-certify its plan, but the Regional Administrator can decide it needs a Professional Engineer's certification instead.
One oil spill can set off three separate reports, and each one has its own trigger, recipient, and clock. Most facilities handle the first two well because they're phone calls made while the spill is still happening. Start with safety, though. If anyone's hurt, there's a fire risk, or oil is heading toward a storm drain or stream, call 911, stop the source if you can do it safely, and get containment in place before you think about paperwork.
| Report | Who receives it | Timing | What triggers it |
|---|---|---|---|
| Phone report | National Response Center, 1-800-424-8802 | Immediately, once you know about the discharge | Any harmful quantity of oil reaching navigable waters or adjoining shorelines, which under 40 CFR Part 110 includes a discharge that leaves a sheen or discoloration on the water |
| Phone report | Pennsylvania DEP, 1-800-541-2050 statewide | Immediately | A spill that causes or threatens pollution of waters of the Commonwealth under the Clean Streams Law and 25 Pa. Code Section 91.33 |
| Written submission | EPA Regional Administrator (Region 3 for Pennsylvania), with a copy to the state | Within 60 days | More than 1,000 gallons in one discharge, or more than 42 gallons each in two discharges within 12 months, to navigable waters or adjoining shorelines |
EPA's own guidance says a discharge that's reportable under the SPCC rule goes to both the NRC and EPA, so the call and the written submission are two separate obligations rather than one report made twice. The NRC call is about getting responders moving. The 112.4 submission is a look back at what failed, what you fixed, and whether your oil spill plan needs to change. We cover the sheen threshold in more detail in our article on when you have to report an oil spill.
One caution on the DEP side. Pennsylvania has been working on changes to its spill notification regulation, so confirm the current requirements with DEP when a spill happens rather than relying on an older checklist. And if the oil came from a regulated storage tank, DEP's tank program can carry its own reporting rules on top of these.
The SPCC rule sets two triggers in 40 CFR 112.4(a). Either one starts a 60-day window, and both count only oil that reaches navigable waters or adjoining shorelines.
| Trigger | Threshold | Deadline |
|---|---|---|
| One large discharge | More than 1,000 U.S. gallons in a single discharge | 60 days |
| Two repeat discharges | More than 42 U.S. gallons each, in two discharges within any 12-month period | 60 days |
The gallon counts refer to oil that reaches the water, not to everything that spilled. If a tank failure releases 3,000 gallons and your dike holds all of it, you haven't hit either trigger, though you may still have cleanup and DEP obligations. If 60 gallons of hydraulic oil runs off your pavement into a creek, that spill counts toward the second trigger. EPA also treats the entire volume of a discharge as oil for these purposes, so if oil and water mix, you can't subtract the water to get under the line.
The second trigger catches people because the first spill alone doesn't require anything. Say 50 gallons reaches a ditch that drains to a stream in March, and 60 gallons does the same in November. The November spill is the one that puts you over, so keep a dated record of every discharge to water, even the ones that seem small. The rule counts the 60 days from the time the facility becomes subject to the requirement, which in practice means the spill that crosses the line. When you're unsure which date started your clock, assume the earlier one.
Gray areas exist. Whether a roadside ditch, a storm sewer, or a seasonally dry channel counts as navigable waters can turn on the facts, so a close call deserves a careful review before anyone decides no report is needed. Also keep in mind that these triggers only apply to facilities subject to the SPCC rule. If your oil storage sits under the threshold, 112.4 doesn't apply to you, though the NRC and DEP reporting still does.

The rule lists nine items, and the first few are simple facility basics. The substance is in items five through eight, where EPA wants to see what failed, what you did about it, and what you're changing so it doesn't happen again.
| Item | What EPA asks for |
|---|---|
| 1 and 2 | Facility name and your name |
| 3 | Facility location |
| 4 | Maximum storage or handling capacity and normal daily throughput |
| 5 | Corrective actions and countermeasures you took, including repairs and replacements |
| 6 | A description of the facility, with maps, flow diagrams, and topographical maps as needed |
| 7 | The cause of the discharge, including a failure analysis of the system or subsystem that failed |
| 8 | Additional preventive measures you've taken or are considering to keep it from recurring |
| 9 | Any other information the Regional Administrator reasonably requires about the plan or the discharge |
The failure analysis is the part that takes real work. A statement like "the valve leaked" won't do much for you. EPA wants to know why it leaked, whether it was a maintenance gap, a missed monthly inspection, an operator error during a transfer, or a design problem, and what in your SPCC Plan was supposed to catch it. Your submission should also match what you told the NRC and DEP. Pull the original reports, incident logs, photos, and cleanup records together before you start writing, because inconsistencies between them are what draw follow-up questions.
You also have to send a complete copy of the submission to the state agency responsible for oil pollution control, which for most Pennsylvania facilities means DEP. The state agency can review it and make recommendations to EPA about further procedures, methods, or equipment. For where to send the submission itself, check EPA Region 3's current instructions or use the contact form on EPA's oil spill prevention pages, since submission details can change. These are written statements to a federal regulator about the cause of a spill, and spills can bring enforcement and liability questions, so many facilities have an environmental attorney review the submission before it goes out. Our overview of SPCC violations and fines shows what's at stake when an inspection finds a gap.
The Regional Administrator reviews your submission, any recommendations from the state, and sometimes an on-site review of your plan. If the plan doesn't meet the requirements of the rule, or if changes are needed to prevent and contain discharges, EPA can require you to amend it. Most facilities never see a formal amendment demand, but the process is spelled out, and the deadlines are short enough that you should know them before a letter arrives. We cover who inspects and enforces in more detail in our guide to SPCC enforcement.
| Step | What happens | Timing |
|---|---|---|
| Proposed amendment | EPA sends the proposed terms by certified mail or personal delivery | You have 30 days from receipt to respond in writing with information, views, and arguments |
| Decision | EPA either notifies you of a required amendment or rescinds the notice | No fixed deadline stated in the rule |
| Amend the plan | You revise the SPCC Plan as required | Within 30 days of the notice, unless EPA sets another date for good cause |
| Implement | You put the amended plan into practice | As soon as possible, and no later than six months after amending, unless EPA specifies another date |
| Appeal (optional) | You appeal in writing to the EPA Administrator, with a copy to the Regional Administrator | Within 30 days of the notice; the Administrator decides within 60 days of receiving the appeal |
Notice how little room that leaves. If you don't have a current SPCC Plan that reflects what your facility looks like today, a 30-day amendment clock is a hard place to start. If you already have a plan, keep it current as a normal habit, and if it's more than five years old, the five-year review is overdue regardless of any spill. Our article on when to update your SPCC Plan explains what triggers an amendment outside of a spill.
A qualified facility is a smaller one, with 10,000 gallons or less of total aboveground oil storage, that can self-certify its own SPCC Plan instead of paying a Professional Engineer to review and certify it. Facilities with no single aboveground container over 5,000 gallons use the Tier I template, and the rest write a Tier II self-certified plan. You'll see the same two numbers in the qualification test that appear in the 112.4 triggers, and that's by design: no single discharge over 1,000 gallons and no two discharges over 42 gallons each within any 12-month period, counting back three years from the date you self-certify, or since the facility became subject to the rule if that's less than three years. Discharges caused by natural disasters, acts of war, or terrorism don't count.
| Situation | Effect on self-certification |
|---|---|
| A reportable discharge falls inside the three years before you would self-certify | You don't meet the criteria, so the plan needs a Professional Engineer's certification |
| A reportable discharge happens after you've already self-certified | No automatic loss of eligibility, but the Regional Administrator reviews your report and can decide you must amend the plan and have a PE certify it |
| Aboveground storage grows past 10,000 gallons | You lose eligibility, and a PE must certify the plan within six months of the change |
| You use the inspection-and-monitoring option for oil-filled operational equipment | Eligibility depends on that equipment's discharge history, not the whole facility's |
The second row is the one to focus on after a spill. EPA's guidance says a facility that self-certified and then has a reportable discharge doesn't automatically lose eligibility, and it also says the Regional Administrator decides whether the plan has to be amended and PE-certified after reviewing the report. In other words, your 112.4 submission is also your argument for why self-certification should stay in place. A clear failure analysis, real corrective actions, and sensible preventive measures give the Regional Administrator a reason to leave your status alone. A thin submission invites the opposite.
If a PE certification does become necessary, it's a separate step with its own cost and timeline. We work with an outside professional engineer in the state where the plan applies, and the engineer reviews, stamps, and seals the plan after our team develops it. You can read more about the difference between plan types in our articles on Tier I self-certified plans, Tier II self-certified plans, and when a Professional Engineer is required.
When a spill crosses one of the 112.4 triggers, we help you pull the facts together and write the submission so the cause, the corrective actions, and the preventive measures all line up with your plan and with what you've already told the NRC and DEP. We'll also review your SPCC Plan against what went wrong, and if you don't have a plan yet and you're subject to the rule, we can tell you what you need and build it. If EPA requires an amendment or a PE certification, we handle the plan work and coordinate the outside engineer. Senior staff do the work, not a handoff to someone junior.
We should be clear about the limits. We're not a law firm, so if the spill has enforcement or liability angles, bring in an environmental attorney. Emergency cleanup belongs to a spill response contractor. And if your spill didn't meet either trigger, you may not need us at all. You'd document it, keep it in your records, and make sure the cause is fixed. There's no pressure either way. You can call us, email us, or fill out the form on our website, and if you'd like to talk through a spill or a plan, just contact RMA and we'll tell you honestly where you stand. If the plan itself needs work, our article on getting an SPCC Plan updated explains what to expect.
Learn everything about SPCC plans, including requirements, costs, and timelines to ensure your facility complies with federal oil storage regulations.
Not sure whether your facility needs an SPCC Plan? Have an existing plan that's due for review? Or do you already know you need one and just want to get the project moving?
Tell us a little about your Pennsylvania facility, the oil you store, and what you're trying to accomplish.
RMA can help you understand which requirements apply, whether you need a new plan or an update, what the project would involve, and what it may cost.
There's no need to have everything figured out before reaching out. That's what we're here to help with.
Want to dig deeper? Check out these additional resources to get a clearer understanding of the SPCC world and how it applies to your facility.
Tags: Pennsylvania SPCC Plans
Whether you need help with a single requirement or want to hand off your entire environmental program, we get it done right, the first time. You'll feel protected, confident in your company's regulatory standing, and ready for whatever comes next.
Tel: 888-RMA-0230 | Email: info@rmagreen
Copyright © Resource Management Associates