Written By: Doug Ruhlin | Last Updated: November 16, 2026
Time to Read 13 Minutes
If you run a quarry or mine in New Jersey, the rain that falls on your pit, stockpiles, haul roads, and plant area doesn't just soak in and disappear. When it runs off your site, collects in a basin, or gets pumped out of the ground, NJDEP treats it as an industrial discharge, and for mines and quarries the permit written for that situation is the R13. It's a general permit, which means NJDEP wrote it once for a whole category of operations and each facility applies for coverage under it. The R13 authorizes stormwater and certain process wastewater discharges to surface water, along with stormwater-only discharges to groundwater, for mining and quarrying operations that fall under a specific list of industry codes.
Below, we'll explain the R13 in plain terms: who it covers, what kinds of water it deals with, how it differs from New Jersey's other industrial stormwater permits, and what it generally asks of an operator. We'll also be straight about the places where the answer depends on your site and the current permit text. If you'd rather skip ahead and talk to someone, you can reach out to RMA anytime, and we'll tell you honestly whether you need our help.
TL;DR
The R13 is NJDEP's general permit for mines and quarries in specific industry codes. It covers stormwater and certain process wastewater going to surface water, and stormwater only going to groundwater. Mining and quarrying can't use the Basic Industrial Stormwater permit (5G2), and sand and gravel pits with no surface water discharge may fit a separate permit called the RSG. Expect to apply for coverage, keep a written stormwater pollution prevention plan, and follow the monitoring and reporting terms in the current permit, which vary by the kind of water leaving your site.
New Jersey regulates industrial discharges through NJPDES, the New Jersey Pollutant Discharge Elimination System, which is the state's version of the federal NPDES program. Instead of putting every industrial facility under one stormwater permit, NJDEP uses a basic permit for most facilities, a group of industry-specific general permits for operations with their own pollution profiles, and individual permits for sites that don't fit either one. The R13, formally the Mining and Quarrying Activity stormwater general permit (NJPDES permit number NJ0141950), is one of the industry-specific permits. Our guide to which NPDES permit you need explains how general, individual, and no exposure options fit together.
The reason mines and quarries get their own permit is that they deal with things a warehouse or machine shop never does. You're moving large volumes of rock, soil, and fines, and that material can wash into a stream as suspended sediment. Many sites also have settling basins, pit water, washing and screening equipment, and maintenance areas on the same property. A permit written specifically for the industry can address those realities directly, and that's why landing on the right permit matters. Each New Jersey general permit has its own plan contents, forms, and conditions.
The R13 is tied to industry codes, specifically SIC codes. An SIC code, short for Standard Industrial Classification code, is a four-digit federal number that describes the main thing a business does at a specific location. NJDEP lists the codes the R13 applies to as 1411, 1423, 1429, 1442, 1446, and 1459, along with the matching NAICS codes, which are the newer federal classification. In everyday terms, those codes cover operations like dimension stone, crushed and broken stone, construction sand and gravel, industrial sand, and clay and similar minerals. NJDEP treats the broader group of mining and quarrying operations (SIC codes 10 through 14) as industrial for stormwater purposes, so if you mine or quarry anything, assume the stormwater rules are in play and check which permit applies.
Coverage doesn't stop at the edge of the pit. The rain that touches your crusher, screening plant, stockpiles, haul roads, loading areas, and equipment maintenance areas is what regulators call stormwater associated with industrial activity. If your property also has a ready-mix plant or an asphalt plant, those operations may point toward different New Jersey permits than the one covering your quarry, and how that plays out depends on how NJDEP authorizes the site and how the operations share drainage. Our concrete industry page covers the work we do for producers who run both aggregates and concrete.
Three kinds of discharge come up with the R13. The first is stormwater going to surface water, meaning runoff that leaves your site and reaches a stream, ditch, or other waterway. The second is stormwater going to groundwater, which happens when runoff is directed to an infiltration area or otherwise soaks into the ground on site. NJDEP uses the abbreviation DGW for discharges to groundwater, and you'll see it in permit documents. The third is certain process wastewater going to surface water. Process wastewater is water that's used in or produced by your operation instead of falling on it as rain, such as wash water or water pumped from the pit.
That third category is where operators most often have questions, and where we want to be careful. NJDEP's own description of the R13 says it authorizes "certain" process wastewater to surface water, and the word certain is doing real work. The agency has described the permit as addressing process water from mine dewatering and setting conditions on it, but which of your discharges qualify, and what limits and monitoring apply to them, is spelled out in the permit text itself. We'd rather tell you to read the current permit and confirm your discharge against it than guess at it for a site we haven't seen. Water that goes somewhere other than a stream or the ground, like a sewerage authority, is a separate question with separate approvals. Our article on the difference between stormwater and process water walks through why the distinction trips people up.

Most of the confusion around the R13 comes from its neighbors. NJDEP states that mining and quarrying activities are no longer authorized under the Basic General Permit (5G2) or the Construction General Permit (5G3), so an older file at your site that points to either one deserves a second look. The sand and gravel permit (RSG) is a separate general permit for sand and gravel operations whose stormwater goes only to groundwater. NJDEP notes that sand and gravel operations previously authorized under the R13 with no surface water discharge may be eligible for the RSG instead. Here's how the pieces line up.
| Permit | Written for | Water it covers | Where mines and quarries land |
|---|---|---|---|
| R13 (Mining and Quarrying Activity) | Mining and quarrying operations in the listed SIC codes | Stormwater and certain process wastewater to surface water; stormwater only to groundwater | The industry-specific permit for mines and quarries |
| RSG (Sand and Gravel Activity) | Sand and gravel mining and quarrying operations | Stormwater to groundwater | Possible for sand and gravel operations with no surface water discharge |
| 5G2 (Basic Industrial Stormwater) | Regulated facilities without an industry-specific permit | Industrial stormwater | Not available for mining and quarrying |
| Individual NJPDES permit | Facilities that don't fit a general permit | Site-specific conditions set by NJDEP | A possibility if your operation doesn't fit the R13 |
Two questions sort most sites. First, what do you mine or quarry, which tells you whether your SIC code is on the R13 list. Second, where does your water go, which separates the R13 from the RSG. If your site drains to a stream or ditch, the RSG probably isn't available to you. If something about your operation doesn't fit any general permit, NJDEP writes an individual permit with site-specific terms, and our guide to the individual NJPDES industrial permit explains when that happens. For a broader look at how New Jersey handles stormwater, see NJPDES stormwater permit requirements in plain English.
The starting point is getting coverage. A facility requests authorization under the R13 by submitting NJDEP's NJPDES application paperwork, which includes the general NJPDES Form 1 or RFA Form 1 and a supplemental form specific to the R13, along with the items on NJDEP's R13 checklist. RFA stands for Request for Authorization, which is the term New Jersey uses for applying to join a general permit. NJDEP takes time to review these, so it helps to start early, and our article on how long a New Jersey stormwater permit takes sets expectations.
The centerpiece after that is the written plan. New Jersey's rules call it a Stormwater Pollution Prevention Plan, or SPPP, and you'll also hear it called an SP3 or just a stormwater plan. We use SWPPP, the term most of the industry uses, and that's what we'll call it here. The R13 requires one, and NJDEP publishes an attachment to the permit that spells out what the plan has to contain. A good SWPPP describes your site, shows how water flows across it, identifies what could pollute that water, and lays out the best management practices, or BMPs, you use to keep sediment and other pollutants out. For mines and quarries, that usually means things like controlling sediment from stockpiles and haul roads, managing settling basins, and keeping dust and fuel and oil areas from contributing to runoff. Our guides on what a SWPPP is and stormwater BMPs go deeper on both. NJDEP also provides a certification form for facilities to certify their plan, so ask which certifications your authorization requires and when.
Monitoring and reporting is where we'll be careful not to oversimplify. What you sample, how often, and what gets reported depends on which discharges you have, and the R13 treats stormwater and process wastewater differently. We're not going to list parameters or frequencies here, because they're set in the current permit and general permits get renewed on NJDEP's schedule. Work from the current version of the permit, not an old copy from a file cabinet. Where sampling applies, we explain why your own people should take the samples in why you should take your own stormwater samples, and discharge monitoring reports explains the paperwork that follows. The people carrying out the plan also need to know what's in it, which is why training pays off whatever the permit's minimums say. Our online training library is a good starting point.
The R13 is an operating permit. It covers stormwater and process water from a mining or quarrying operation, and it doesn't take the place of the requirements that come with construction. Building a new processing plant, adding roads or basins, or disturbing new ground can bring construction-phase stormwater and soil rules, such as soil erosion and sediment control certification through the local Soil Conservation District and stormwater management design for major development under N.J.A.C. 7:8. NJDEP has also removed mining and quarrying from eligibility under the Construction General Permit (5G3), so don't assume an old construction authorization covers quarry activity.
We don't prepare construction-phase permits or approvals. Your engineer, contractor, or a soil erosion specialist handles those, and we're glad to help you work out what the construction phase needs and point you toward the right people. Once the operation is running, you'll need the right operating permit, a current SWPPP, and the monitoring and certifications that go with it, and that's where we come in.
We do mining NJPDES work and have plenty of experience with the mining industry, and we're based in New Jersey, so NJDEP's permit categories are familiar ground. We can confirm which permit fits your site, prepare the request for authorization and forms, write or update your SWPPP, and build an inspection routine your team can keep up. We train your staff to inspect and sample correctly, since we don't take your samples ourselves. Storm events don't wait on a consultant's calendar, and your own people know the site. After you're permitted, we offer annual support if you want it, from reminders and result reviews to inspection prep, and you can keep it as hands-off or hands-on as you like. What it costs depends on things like how many discharge points you have, how complex the site is, and whether a plan already exists, and our NPDES pricing calculator gives you a ballpark.
We're not the right fit for every job. We don't do engineering design or construction work, so settling basin design or a water treatment system would go to an engineer. A very large portfolio of sites may not suit a small firm like ours, and if you're shopping on the lowest price or the fastest turnaround, we're probably not your match. We're not always the cheapest consultant, though we're usually a little less expensive than an engineering firm. And if your SWPPP is current and your team has the permit well in hand, you may not need us at all, and we'll say so. Our article on getting a stormwater permit yourself explains what that looks like.
If you'd like to talk through your site, you can call us at 888-RMA-0230, email info@rmagreen.com, or fill out the form on our website. You can also contact RMA directly. There's no pressure and no obligation, and we're happy to tell you where you stand.
Learn about NPDES Stormwater Permits, timelines, costs, and compliance essentials for businesses to manage environmental responsibilities effectively.
Maybe you know you need a permit but don't know which one. Maybe you have an old 5G2 authorization, a stormwater plan that's out of date, or a letter from NJDEP asking for information. Or maybe you're just trying to figure out whether your outdoor operations count as industrial stormwater exposure.
Tell us a little about your New Jersey facility and what you're trying to solve. RMA can review the situation, explain the likely permitting options, and talk through the work, timeline, and cost involved.
Looking for more info? Check out all of our New Jersey NJPDES & stormwater articles here!